ANTE User Manual

Project Details

View comprehensive information about a specific project. Access project data, tasks, documents, and manage project activities.

Overview

The Project Details page provides a complete view of a single project. You can see all project information, manage tasks, track progress, and access project-related dialogs.

A project's Overview: headline numbers, the tab bar, schedule summary, and the progress chart.
  1. 1Fields, Team, and Settings โ€” the project-level actions
  2. 2Counters โ€” health, work accomplished, days left, overdue tasks
  3. 3Tab bar โ€” your views first, then the analysis tabs
  4. 4Schedule summary โ€” progress, next milestone, and milestone roadmap
  5. 5Progress Chart โ€” switch between S-Curve and Burndown
  6. 6Overview widgets: blockers, overdue tasks, and task aging

Page Layout

Project Header

  • Project Name - Displayed prominently at the top
  • Breadcrumbs - Navigation path (Dashboard โ†’ Project List โ†’ Project Name)
  • Action Buttons:
    • Work Accomplishment - Record project progress
    • Task Management - Manage project tasks
    • Bill of Quantity - Manage materials and quantities

Project Overview Section

  • Project information summary
  • Key metrics and statistics
  • Project status and timeline
  • Budget information
  • Team members

Project Content

  • Detailed project information
  • Related tasks
  • Documents and files
  • Timeline and milestones
  • Activity feed

Actions Available

Header Actions

  • Work Accomplishment - Opens Work Accomplishment Dialog
  • Task Management - Opens Task Management Dialog
  • Bill of Quantity - Opens Bill of Quantity Dialog

Project Actions

  • Edit Project - Modify project information
  • Add Task - Create new task for this project
  • Upload Document - Add files to project
  • Add Team Member - Assign team members
  • Update Status - Change project status
  • View Reports - Generate project reports
The project's Team, opened from the Team button in the header โ€” add members and set each one's team role here.

Dialogs

Bill of Quantity Dialog

Purpose: Manage project materials, quantities, and costs.

How to Open: Click Bill of Quantity button in project header.

Features:

  • Add materials and items
  • Set quantities and units of measure
  • Enter unit costs
  • Calculate total costs
  • Organize by categories
  • Export BOQ to PDF or Excel
  • Print BOQ

Fields:

  • Item Code - Material/item identifier
  • Description - Item description
  • Unit - Unit of measure (pcs, kg, m, etc.)
  • Quantity - Required quantity
  • Unit Price - Cost per unit
  • Total - Automatically calculated

Actions:

  • Add Item - Add new material/item
  • Edit Item - Modify existing item
  • Delete Item - Remove item
  • Save - Save changes
  • Export - Export BOQ
  • Print - Print BOQ
  • Close - Close dialog

Work Accomplishment Dialog

Purpose: Record and track project progress and accomplishments.

How to Open: Click Work Accomplishment button in project header.

Features:

  • Record work accomplishments
  • Add progress notes and descriptions
  • Upload supporting documents/photos
  • Set completion percentage
  • Track accomplishment dates
  • View accomplishment history

Fields:

  • Date - Date of accomplishment
  • Description - What was accomplished
  • Progress % - Completion percentage
  • Notes - Additional details
  • Attachments - Upload photos or documents
  • Category - Type of accomplishment

Actions:

  • Add Accomplishment - Record new accomplishment
  • Edit - Modify existing entry
  • Delete - Remove accomplishment
  • Upload File - Add supporting documents
  • Save - Save changes
  • Close - Close dialog

Task Management Dialog

Purpose: Manage all tasks related to the project.

How to Open: Click Task Management button in project header.

Features:

  • View all project tasks
  • Create new tasks
  • Update task status
  • Assign team members
  • Set priorities and due dates
  • Filter tasks by status
  • View task details

Task List:

  • Shows all tasks linked to the project
  • Displays task status, assignee, due date, priority
  • Click on task to view details

Actions:

  • Create Task - Add new task to project
  • Edit Task - Modify task information
  • Update Status - Change task status
  • Assign - Assign to team member
  • Delete - Remove task
  • Filter - Filter by status, assignee, priority
  • Close - Close dialog

Planning Helpers

The project details page includes a few helpers that take some of the busywork out of planning.

Project Setup Wizard

When a project still has no tasks, a Set up your project panel replaces the usual statistics cards near the top of the page. It shows a progress bar and a short checklist so a brand-new project has a clear starting point.

The checklist covers four steps:

StepWhat it asks you to do
Add team membersInvite your team to the project. Marked complete once the project has more than just its creator.
Create your first tasksBreak the project into actionable tasks. Marked complete once the project has at least one task.
Set milestonesDefine key deliverables and deadlines. Marked complete once the project has at least one milestone.
Configure project fieldsCustomize the statuses and workflow used by the project.

Click any step to jump to where you complete it. As steps are done, their checkmarks fill in and the progress bar advances. Once the project has at least one task, the wizard disappears on its own and the normal statistics cards take its place. To hide it sooner, click Skip setup in the top-right corner of the panel โ€” that project will keep the cards in view from then on.

The Fields panel, where the project's task statuses, milestones, and team roles are defined.

Auto Assign Tasks

Auto Assign saves you from assigning tasks one at a time. You choose which team roles should be assigned automatically and how members within each role share the work, then run it across the project's tasks.

How to open: On the project details page, click the Settings button (gear icon) in the header, then choose Automate. The Auto Assign Tasks dialog opens.

Set up team roles first

Auto Assign works from your project's team roles. If none exist yet, the dialog shows "No team roles defined. Add team roles in the Fields tab first." Define your roles on the Fields tab before using it.

How to use it:

  1. Tick the checkbox next to each team role you want to assign automatically. Enabled roles expand to show their settings.
  2. For each enabled role, choose a Strategy:
    • Assign All Members โ€“ Every member with that role is assigned to the matching tasks.
    • Round Robin โ€“ Tasks are shared out evenly, one member after another in turn.
  3. Review the Members shown under each role. Roles with no one assigned display a No members note.
  4. Pick a Scope for the run:
    • Unassigned tasks only โ€“ Only tasks with no one assigned yet are touched.
    • All tasks (overwrite existing assignments) โ€“ Every matching task is reassigned, replacing current assignees.
  5. Finish with either:
    • Save Rules โ€“ Saves your role settings for next time without assigning anything yet.
    • Run Auto Assign โ€“ Saves the rules and immediately assigns the tasks. Available only when at least one role is enabled.

๐Ÿ“Œ Tip: Use Unassigned tasks only to fill in the gaps, and All tasks when you want to reset every assignment from scratch.

AI Time Estimate

AI Time Estimate uses AI to read each task's title, description, checklists, and subtasks and suggest how long it should take (assuming an 8-hour workday). You choose a Scope โ€” Only tasks without estimates or All tasks (overwrite existing estimates) โ€” and the run reports the estimated time and a short reasoning note for each task.

Not currently available from the menu

This tool exists in the system but has no working button on the project details page yet โ€” there is no menu item that opens it. It is documented here for reference; expect a way to launch it in a future update.

Overview Tab Widgets

The Overview tab opens with two full-width widgets that summarize the project's journey (the schedule summary, then the progress chart):

  • Schedule Summary โ€” the same summary your client sees on the share link, at the top of the tab: overall progress, the next milestone with a countdown, "Waiting on client" (with a View action items link that opens Client Pending), and on track / at risk / delayed / done / blocked counts, followed by the last-updated and baseline stamps. Below it sits a milestone roadmap(each milestone's target date, its forecast or finish date, and a late or on-time badge), then N items changed since your last visit, Coming up next (due in the next 14 days, plus anything overdue) and Recently completed (finished in the last 14 days). Unlike the share link, it counts every task, including internal ones, as noted under the summary. Click any item to open the task. This replaces the old milestone strip.
  • Progress Chart โ€” a line chart with S-Curve and Burndown tabs in its upper-right corner (S-Curve is shown by default). S-Curve plots cumulative completed tasks against the planned pace across the whole project timeline, with a vertical marker at today's date. Burndown plots remaining tasks against an ideal pace over the last 30 days.

Project Health

The Project Health stat card at the top of the project page shows a single percentage score (0โ€“100%). The score is a weighted composite of five factors: Schedule (25%), Overdue (25%), Blockages (20%), Issues (15%), and Activity (15%). For a brand-new project with no tasks yet, the card shows Not Started instead of a score.

Click the Project Health card to open the Project Health dialog:

  • A gauge shows the overall score out of 100.
  • Below it, five factor cards show each factor's own score and a short detail line (for example, how many tasks are overdue, or how old the oldest open issue is).
  • Click any factor card to jump to the related part of the project and close the dialog:
    • Schedule and Blockages jump to the matching widget on the Overview tab.
    • Overdue jumps to the Overdue Tasks widget on the Overview tab.
    • Issues switches to the Issues Log tab.
    • Activity switches to the Activity Log tab.
Tip

The Activity factor is based on how recently something happened in the project's Activity Log compared to your organization's Client Interaction Frequency (set on the Project Settings page, or overridden per project). A quiet project scores lower on Activity.

Sharing a Project

Click Settings (gear icon) in the project header, then Share, to generate a public, passcode-protected link a client can open without an ANTE account. The link shows the project's live status, milestones, and timeline, and lets the client comment on individual tasks โ€” internal staff notes and activity are never exposed. See the full Sharing a Project page for the dialog's fields and what the client sees.

Analysis Tabs

Beyond tasks and timelines, every project carries a set of analysis tabs that help an implementation team see everything that happened in the project, capture requirements, flag issues, compare needs against system capability, manage risk, and chase items the client still owes you.

These tabs live in the tab bar across the top of the project detail page:

TabWhat it tracks
Activity LogA consolidated, day-grouped timeline of everything in the project โ€” task completions, comments, meetings, and emails โ€” plus events you add manually
FilesEvery file connected to the project โ€” task attachments, Activity Log post attachments, direct uploads, Files library files, and process/comment attachments โ€” in one searchable, filterable list
NotesWorkspace notes linked to the project โ€” write-ups, meeting notes, and docs your team keeps alongside the project
RequirementsRequirement checklists gathered from the project's tasks, with progress and client-pending flags
Issues LogTasks flagged as issues โ€” bugs, change requests, or clarifications raised against the project's work
Fit/GapEach client requirement compared against current system capability
Risk RegisterProject risks, their likelihood and impact, and mitigation plans
Client PendingTasks flagged as waiting on the client to deliver something
DiscoveryClient onboarding questionnaires sent for this project and their progress, plus every file clients uploaded

Two of these tabs โ€” Fit/Gap and Risk Register โ€” share the same editable spreadsheet experience, so once you learn one you know them both; see Working in a Spreadsheet Tab below. Requirements works differently and is described in its own section. Activity Log, Issues Log, and Client Pending are card-based views built on top of tasks โ€” each card opens the same Task Detail dialog you use everywhere else in Ante, and they are described in their own sections below. Files and Notes are management views rather than analysis tabs, but live in the same tab bar โ€” see Files Tab and Notes Tab below. Discovery is its own module โ€” see Discovery Tab below and the full Discovery module page.

Choosing Which Tabs Are Visible

Not every tab is shown by default. Overview, Knowledgebase, Activity Log, Files, Notes, Requirements, Issues Log, Client Pending, and Discovery are visible out of the box; Fit/Gap, Risk Register, Tasks, and Processes start hidden to keep the bar tidy. Click the eye icon at the right end of the tab bar to open the Visible Tabs list, then tick the tabs you want to see. The Overview tab is always on and cannot be hidden. Your choices are remembered per project.

The tab you have open is also remembered in the page address, so the project page returns to the same tab even if you refresh.

The Tasks tab, one of the tabs hidden by default: standalone tasks tagged to the project, plus tasks created by its processes.

Working in a Spreadsheet Tab

The Fit-Gap and Risk Register tabs use the same editable spreadsheet.

The Fit-Gap tab โ€” the shared spreadsheet layout, edited cell by cell.

Adding a row

  • Click Add Row at the bottom of the table to add a new, blank entry. New rows arrive pre-filled with sensible defaults โ€” for example, a new risk starts with status Identified.
  • To insert a row directly beneath an existing one, right-click the row and choose Add Row Below.

Editing cells

  • Click any editable cell and type to change its value. Your edit saves automatically when you move off the cell โ€” there is no separate Save button.
  • Date cells open a date picker. Drop-down cells (such as Status, Priority, or Category) show a list of choices to pick from.
  • A few columns are calculated for you and cannot be edited (for example, the Score on a risk, or the auto-generated reference code on each row).

Reordering rows

  • Hover over a row and drag it by the handle on its left to change its order in the list. The new order is saved.

Deleting a row

  • Right-click the row (or click the โ‹ฎ menu at its right end) and choose Delete Row, then confirm. Deletion cannot be undone.

Wider view

  • Use the Expand button on the toolbar to wrap long text in cells; click Compact to switch back to the tighter view.

Opening a Row's Detail Panel

Click the row number to open its detail panel. The panel shows that row's fields on the left and a discussion Activity / comments area on the right, so your team can talk through an item in one place. Long-text fields (descriptions, mitigation plans, remarks) sit in a main area, and reference fields collapse under a Details section.

On the Risk Register tab, the panel header also offers:

  • Mark as Resolved โ€” sets the row to its "done" status (Mitigated). Once done, a Resolved badge appears in place of the button. The Fit/Gap tab does not have this button.

Exporting and Importing with Excel

The Fit-Gap and Risk Register tabs each have a toolbar above the table with these actions:

  • Export โ€” download the current table as an Excel file.
  • Download Template โ€” get a blank Excel file with the correct columns, ready to fill in.
  • Import โ€” upload a filled-in Excel file to add many rows at once.

๐Ÿ“Œ Tip: Use Download Template first, fill it in offline, then Import it โ€” handy when a client sends you a long list of fit-gap findings or risks.

Requirements Tab

The Requirements tab gathers every requirement checklist attached to the project's tasks into one place, so you can see โ€” and complete โ€” them without opening each task.

The Requirements tab: every requirement from the project's tasks, gathered in one list.

What you see

  • A summary bar at the top showing the total number of requirement items, how many are Completed, how many are still Pending, and (when any exist) how many are flagged Client Pending, plus an overall percent-complete progress bar.
  • A grid of task cards, one per task that has requirements. Each card shows its completion percentage, a completed-over-total count, and an indicator if any items are waiting on the client.

Searching and filtering

  • Use the search box to find requirements by task name, checklist name, or item.
  • Use the status filter to show All, Completed, or Incomplete items only.

Completing a requirement

  1. On a task card, click Show Requirements to open its detail dialog.
  2. Each requirement item shows what kind of answer it needs โ€” a text input, a longer text field, a file upload, an image, or a choice from a list.
  3. Fill in or upload the value directly in the dialog. Completed items are marked with a check.

Flagging an item as Client Pending

Each requirement item has a small CP (Client Pending) button. Click it to flag that the item is waiting on the client โ€” this creates a task flagged as client-pending, which then also appears in the Client Pending tab, and the button label switches to show CP plus that task's status (for example, CP ยท pending). Click again to remove the flag.

Adding a new requirement checklist

  1. Click Add Checklist (or the add button shown when the tab is empty).
  2. In the dialog, choose the Task the checklist belongs to (required) and enter a Checklist Title (required).
  3. Add one or more requirement items. For each item, enter a Title (required) and choose a Field Type:
    • Input โ€” short text
    • Text Field โ€” longer text
    • File Upload โ€” a document
    • Image โ€” a picture
    • Option โ€” a choice from a list (enter the choices separated by commas)
  4. Tick Required for any item that must be answered.
  5. Click Create.

Activity Log Tab

The Activity Log is a consolidated, day-grouped timeline of everything that has happened in the project โ€” every completed task, task comment, finished meeting, and sent email, plus any events you add yourself. System events (task completions, comments, meetings, emails) are recorded automatically; you only add the manual ones.

The Activity Log: everything that happened in the project, grouped day by day.
The Activity Log reads as plain sentences, and the filter chips narrow it to one kind of event.
Add event: besides what happened, you can name the people involved, link tasks and write the next step.

What you see

  • Events are grouped under day headings (Today, Yesterday, or the full date), newest first.
  • Every row starts with a plain sentence that says who did what, for example "Guillermo completed Load the new basic salaries effective 26 October" or "Decision recorded: overtime is rounded down to 15 minutes". Supporting text, such as the start of a comment or the reason a task is waiting on the client, sits below it in a lighter colour. A small label names the kind of entry, and tasks it refers to appear as chips that open the task. The same wording is used for older entries.
  • A filter bar at the top lets you narrow the feed to All, Tasks, Comments, Meetings, Knowledgebase updates, Client items, Notes, or Logged events (the ones added by hand). The Decisions filter sits right after All: it lists every decision recorded against the Knowledgebase plus every manual entry of type Decision, with who agreed and when, so it is the history of why the plan changed.
  • Every new version of the project Knowledgebase adds an entry naming the sections that changed. A decision that changes the plan adds its own entry, dated the day it was agreed, so you can always see when an agreement was recorded; the Knowledgebase itself shows only the latest plan. Notes recorded straight onto the project (for example meeting minutes written by Claude) appear as "recorded the note".
  • Click Load more at the bottom of the feed to fetch older events.

Adding a manual event

A manual event is a short post with a one-sentence headline. Write the headline as a plain, past-tense sentence that says who did what, for example "Agreed the overtime rounding rule with the client". Avoid codes, commit or pull request numbers and task numbers; use the related-tasks field to link a task instead.

  1. Click Add event.
  2. Choose the event Type: Note, Meeting, Call, Email, Decision, or Milestone.
  3. Write the Headline: one plain sentence, up to 120 characters.
  4. Write the post body in the text box (the details). Use the toolbar to format it โ€” Bold, Italic, Underline, and bullet lists are supported.
  5. Optionally fill People (who was involved, for example "Maria Reyes (client)"), Related tasks (shown as links under the entry) and Next step (what happens next, in one sentence).
  6. Optionally click the paperclip icon to attach files โ€” any file type, not just images or photos, up to 10 per post.
  7. Optionally adjust the Date โ€” it defaults to today, but you can backdate it.
  8. Click Post to save. You need either some text or at least one attachment before you can post.

Manually-added events show a delete (trash can) icon on their row so you can remove them later; automatic system events cannot be deleted from here.

Editing a logged event

A manual event can be corrected after it is posted. Click the pencil icon on its row to change the headline, details, people, related tasks, next step, date or attachments, then save. This is the way to tidy an old entry that reads like code. Automatic entries cannot be edited, but they are always shown in plain words.

Issues Log Tab

The Issues Log shows every task in the project that has been flagged as an issue โ€” there is no separate issue record; an issue is simply a task with its issue flag set. Each card opens that task in the normal Task Detail dialog.

The Issues Log: the project's tasks flagged as issues, each opening its task.

What you see

  • A count of open issues at the top.
  • A grid of issue cards, each showing the Issue badge, the task's priority flag (if set), its title, the issue description, its assignee (or Unassigned), and its due date.

Flagging an existing task as an issue

  1. Open the task's detail view.
  2. In the Activity panel, click the flag icon next to the activity header.
  3. Type what the issue is in the prompt that appears, then click Flag Issue.

The task now shows an issue banner in its detail view (with who flagged it and when) and appears in this tab.

Creating a new task as an issue

  1. On the Issues Log tab, click Add issue.
  2. Enter a Title (required) and a Description.
  3. Click Add issue โ€” this creates a new task, already flagged as an issue, in the project.

Resolving an issue

Open the issue's card to open its Task Detail dialog, then click Resolve Issue on the issue banner.

Client Pending Tab

The Client Pending tab shows every task in the project that is flagged as waiting on the client โ€” again, there is no separate record; it is a flag (and a small set of extra fields) on a task. Each card opens that task in the Task Detail dialog.

The Client Pending tab: everything the project is still waiting on the client for.

Summary cards

At the top of the tab: Pending Items, Overdue (the commitment date has passed), Follow-up Due, Blocking Project, Avg Wait Time, Longest Wait, and Received This Month.

Toolbar: search, filters and grouping

Use the search box (it matches the title, the client contact or the person in charge) and the All statuses and All impacts filters to narrow the list. Group by switches the layout between Section, Status, Impact and Person in charge. Each group can be collapsed, and items that are already Received or Waived move to a Done: received / waived area at the bottom. The toolbar also holds the Add section, Reorder sections, Default plan and Add client-pending buttons.

What you see on a card

  • A status chip (Pending, Received, or Waived), an impact chip, and the days pending.
  • The task title, the Person in charge (the task's assignees, or Unassigned), and the client contact โ€” name, role, and email or phone when known (or No contact).
  • The follow-up progress, for example Follow-up 2 of 3 ยท next 14 Oct. It turns amber with a Follow-up due badge when a follow-up is due, and red with Escalation due when every planned follow-up has been made and the client is still silent.
  • The Promised date (the commitment date) and a Log follow-up button.

Organising items into sections

Each project can have its own sections (for example "Legal documents"). Click Add section and type a Section name; on a section header you can Add item here, Rename section or Delete section โ€” deleting only moves its items to Unsectioned, nothing else is removed. Reorder sections opens a dialog where you drag sections into the order you want, or edit a name and click away to rename it. To move an item between sections, drag its card โ€” this works only while Group by is Section and the search and filters are cleared.

The follow-up plan

A plan says how many times to chase the client and how often. Every item uses the project's Default plan (3 follow-ups, every 3 days, unless you change it). Click Default plan to edit the project default โ€” Number of follow-ups (1 to 20) and Days between follow-ups (1 to 90) โ€” and tick Apply to items using the default to update the existing items too. Any single item can instead use a Custom plan, or go back to Use project default. The next follow-up is due the interval after the last logged follow-up (or after the request date if none is logged yet).

Automatic reminders

The system checks every 15 minutes. When a follow-up is due, the person in charge is notified in the app and in Slack. Once the plan is used up and the client has still not answered, an escalation notice goes out that also reaches the project's person in charge or relationship owner.

Logging a follow-up

Click Log follow-up on a card (or in the task). Pick the Channel (Email, Call, Chat, Meeting or Other), the Date, and a Note on what was said or agreed. The follow-up list shows each entry with who logged it; use Edit or Delete to correct one. Follow-ups counted before logging existed show as "N earlier follow-ups (before logging)".

Creating a new task as a client-pending item

  1. On the Client Pending tab, click Add client-pending.
  2. Enter a Title (required), choose the Section, and the Client contact โ€” the picker suggests contacts already used in this project, or type a new name with its Role, Email and Phone.
  3. Choose the Person in charge, the Impact (Low, Medium, High, or Blocking), the Commitment date, and the Follow-up plan (Use project default or Custom plan).
  4. Click Add item โ€” this creates a new task, already flagged as waiting on the client.

Managing a client-pending item

Open its card to reach the Task Detail dialog, where a Waiting on client panel lets you edit the Client contact, Section, follow-up plan, Impact, Status, Commitment date and remarks. It shows the follow-up progress line, lets you click Log follow-up, and has Mark received for when the item arrives.

The "Client" chip on task rows and board cards

While an item is still Pending, its task shows a small Client chip with the days waiting (for example 5d) in the Project Tracker list and on board cards. Hover it to see Waiting on client, the contact, the days pending, the commitment date, and Follow-up overdue when a follow-up is late (the chip then turns stronger). Received and waived items show no chip.

Tip

You can also create a client-pending task directly from the Requirements tab by clicking a requirement's CP button โ€” see Flagging an item as Client Pending above.

Files Tab

The Files tab is the one place to find every file connected to the project, no matter where it was originally uploaded โ€” task attachments, files attached to Activity Log posts, files uploaded directly on this tab, files in the project's Files folder, and files attached to a process step or a task comment.

The Files tab: every file attached anywhere in the project, in one searchable list.

What you see

  • A search box to find a file by name.
  • Type filter chips: All, Images, Documents, Video, or Audio.
  • A table listing each file's name (with a thumbnail for images), Type, Size, Source (which task, process, comment, or folder it came from โ€” or Project for a direct upload), who Uploaded it, and the Date.
  • A file count at the bottom, with Load more to fetch further pages.

Uploading a file

Click Upload, then pick one or more files of any type from your computer. Each one is added to the project directly (it does not need to belong to a task or a post).

Downloading a file

Click the download icon on a file's row to open or save it.

Deleting a file

Click the trash-can icon on a file's row, then confirm in the dialog. Deleting a file removes it permanently โ€” this cannot be undone.

Knowledgebase Tab

The Knowledgebase tab, placed right after Overview, is the project's main document: one living page that records everything the client and your team have agreed and finalized, always showing the latest plan โ€” people, scope, every setting and business rule, company policies and key dates. It holds no history; decisions are kept in the Activity Log. It is created automatically the first time the tab is opened. Project Creators and Moderators can edit it; other members read it. It has a table toolbar, callout tones including an Internal note that is never shown to the client, an On this page outline, a History list with restore, export and print, and a switch that decides whether the client sees it on the share link. See the full Project Knowledgebase page.

Notes Tab

The Notes tab shows every workspace note linked to the project โ€” a place for write-ups, meeting notes, and docs your team wants to keep alongside the project's tasks and files.

What you see

  • A list of notes linked to this project, each row showing the note's icon, Title (or Untitled if none is set), a text preview, the Author, and how long ago it was last updated.
  • If nothing is linked yet, the tab shows an empty message and a New Note button to get started.

Creating a note from this tab

Click New Note. A blank note is created, automatically linked to this project, and opens straight away in the note editor so you can start typing.

Opening a note

Click anywhere on a note's row to open it in the note editor, without leaving the project page. Inside the editor you can change the note's icon and title (both save automatically as you type), write content using the block editor, Pin the note, Share it with other people or the whole company, or Delete it. Click Open full page in the editor to continue working on the note in its own dedicated workspace page; click the close (โœ•) icon to return to the project's Notes tab.

Unlinking a note

If you authored the note, its row shows an Unlink button. Click it and confirm to remove the note from this project โ€” the note itself is not deleted and stays available to its author; it just no longer appears on this project.

Discovery Tab

The Discovery tab has two sub-tabs, Sends and Files. Sends lists the client onboarding questionnaires that have been shared for this project, each showing its Title, Status (Shared, Opened, In progress, Submitted, or Reopened), Progress (answered/total), and Sent at time. Click Share questionnaire to send a new one โ€” the project is pre-linked automatically โ€” or click a row to open that send's detail page, where you can copy the fill link, reopen a submitted send, or regenerate its passcode. Files rolls up every document uploaded across all of the project's questionnaires into one searchable list, with a column naming which send each file came from โ€” see All Files for a Project. See the full Discovery module page for the complete flow, from building a template to the client's fill experience.

Field Reference

Issues Log

Fields shown on an issue come from the underlying task, plus the issue flag itself:

FieldDescription
TitleThe task's title
DescriptionThe issue description entered when flagging or creating the issue
PriorityThe task's priority: Very Low, Low, Normal, High, or Urgent
Assigned ToThe task's assignee
Due DateThe task's due date
Flagged ByWho flagged the task as an issue
Flagged AtWhen it was flagged

Fit/Gap

FieldDescription
ModuleHRIS, Payroll, Attendance, Leave, Treasury, Reports, or Settings
Process AreaThe business process being assessed
Client RequirementWhat the client needs
Current CapabilityWhat the system does today
PriorityMust Have, Should Have, or Nice to Have
Fit/GapFit, Partial Fit, Gap, Workaround, or N/A
ResolutionStandard Config, Customization, Process Change, 3rd Party Integration, Manual Process, Deferred, or Not Needed
Effort (days)Estimated work required
Assigned ToPerson responsible
Target DatePlanned completion date
Remarks / NotesAdditional notes

Risk Register

FieldDescription
Date IdentifiedWhen the risk was spotted
CategoryTechnical, Resource, Schedule, Scope, Client, Vendor, Data, or Compliance
Risk DescriptionWhat could go wrong
LikelihoodRare, Unlikely, Possible, Likely, or Almost Certain
ImpactNegligible, Minor, Moderate, Major, or Severe
ScoreCalculated automatically from likelihood and impact
StatusIdentified, Mitigating, Mitigated, Occurred, Closed, or Accepted
Mitigation PlanHow you will reduce the risk
OwnerPerson accountable for the risk
Review DateWhen to revisit the risk
Contingency PlanWhat to do if the risk happens anyway

Client Pending

Fields shown on a client-pending item come from the underlying task, plus the client-pending flag's own fields:

FieldDescription
TitleThe task's title
Client ContactWho at the client should provide it
Person in chargeThe task's assignees, who get the follow-up reminders
SectionThe project section the item is filed under, or Unsectioned
Follow-up PlanNumber of follow-ups (1 to 20) and days between them (1 to 90) โ€” the project default or a custom plan
ImpactLow Impact, Medium Impact, High Impact, or Blocking
StatusPending, Received, or Waived
Commitment DateWhen the client promised to deliver
Due DateThe task's due date
Days PendingCalculated automatically
# Follow-upsHow many times you have followed up
Last Follow-upWhen you last chased it
Date ReceivedWhen it actually arrived

At the top of the Client Pending tab, summary cards show Pending Items, Overdue, Follow-up Due, Blocking Project, Avg Wait Time, Longest Wait, and Received This Month.

Activity Log

FieldDescription
TypeTask Completed, Comment, Meeting, Email Sent, or Event (manual)
Category (manual events only)Note, Meeting, Call, Email, Decision, or Milestone
TitleThe event's headline โ€” for manual posts, this is generated automatically from the body text, not typed in separately
DescriptionThe post body (manual events only) โ€” rich text, can include bold/italic/underline/bullet formatting
Attachments (manual events only)Up to 10 files of any type; images show as a thumbnail grid, other files show as a downloadable link
Occurred AtWhen the event happened โ€” defaults to now for manual events, but can be backdated
ActorWho performed the event, when known

Files

FieldDescription
NameThe file's name (with an image thumbnail when applicable)
TypeImage, Document, Video, or Audio
SizeThe file's size
SourceWhere the file came from โ€” the task, process, or comment it's attached to, the folder it's in, or Project for a direct upload
Uploaded byWho uploaded the file
DateWhen it was uploaded

Notes

FieldDescription
IconAn emoji shown next to the note's title
TitleThe note's title (shows as Untitled if not set)
PreviewA short excerpt of the note's content
AuthorWho created the note
Last UpdatedHow long ago the note was last edited

Common Tasks

Viewing Project Information

  1. Navigate to project from Project List or Dashboard
  2. View project details page
  3. Review all project information

Logging a Client Issue

Either flag an existing task or create a new one:

  1. On an existing task โ€” open it, click the flag icon in the Activity panel header, describe the issue, and click Flag Issue.
  2. As a new task โ€” open the project's Issues Log tab, click Add issue, fill in the Title and Description, and click Add issue.
  3. Once resolved, open the task and click Resolve Issue on its issue banner.

Recording a Fit-Gap Finding

  1. Open the Fit/Gap tab and click Add Row.
  2. Choose the Module and enter the Client Requirement and Current Capability.
  3. Set the Fit/Gap result and the planned Resolution.

Registering and Mitigating a Risk

  1. Open the Risk Register tab and click Add Row.
  2. Describe the risk and set its Likelihood and Impact โ€” the Score is calculated for you.
  3. Enter a Mitigation Plan and assign an Owner.
  4. Open the row and click Mark as Resolved once the risk is mitigated.
The Risk Register: one row per risk, scored from its likelihood and impact.

Tracking an Item You're Waiting On

  1. Open the project's Client Pending tab and click Add client-pending (or flag a requirement as CP from the Requirements tab).
  2. Enter the Title, Client contact, Impact, and Commitment date.
  3. Open the card any time to click Log follow-up as you chase it.
  4. Click Mark received on the card once the item arrives.

Recording a Manual Activity Event

  1. Open the project's Activity Log tab and click Add event.
  2. Choose a Type โ€” Note, Meeting, Call, Email, Decision, or Milestone.
  3. Write the post body, optionally attach files, and optionally adjust the Date.
  4. Click Post to save.

Finding and Managing a Project File

  1. Open the project's Files tab.
  2. Use the search box or the type chips (Images, Documents, Video, Audio) to narrow the list.
  3. Click Upload to add a new file directly to the project (any file type).
  4. Click a row's download icon to open/save the file, or its trash-can icon to delete it permanently.

Writing a Project Note

  1. Open the project's Notes tab and click New Note.
  2. The note opens right away in the editor โ€” give it a title and an icon, then start writing.
  3. Use Share to give other people access, or Pin to mark it important.
  4. Click Open full page to keep working on the note in its own workspace page, or close the editor to return to the tab.
  5. If you no longer want the note attached to this project, click Unlink on its row (only the author sees this option) โ€” the note itself is kept, just detached from the project.

Recording Work Accomplishment

  1. Click Work Accomplishment button
  2. Click Add Accomplishment
  3. Fill in:
    • Date of work
    • Description of what was done
    • Progress percentage
    • Upload photos if needed
  4. Click Save

Managing Project Tasks

  1. Click Task Management button
  2. View all project tasks
  3. Create new tasks or update existing ones
  4. Assign tasks to team members

Assigning a Whole Project's Tasks at Once

  1. Make sure your team roles are defined on the Fields tab
  2. Click Settings โ†’ Automate in the project header
  3. Enable the roles you want and pick a Strategy for each
  4. Choose Unassigned tasks only or All tasks
  5. Click Run Auto Assign and review the summary

Creating Bill of Quantity

  1. Click Bill of Quantity button
  2. Click Add Item
  3. Enter material details:
    • Item code and description
    • Unit of measure
    • Quantity needed
    • Unit price
  4. Save item
  5. Repeat for all materials
  6. Export or print when complete

Tips and Best Practices

  • Regular Updates - Update work accomplishments regularly
  • Track Progress - Use progress percentage to monitor completion
  • Document Work - Upload photos and documents as proof of work
  • Manage Tasks - Keep project tasks organized and up-to-date
  • Maintain BOQ - Keep Bill of Quantity current as project progresses
  • Team Communication - Use task comments for team coordination
  • Edits save as you go - The spreadsheet analysis tabs have no Save button, so move off a cell to commit your change
  • Use the detail panel for discussion - Click a row to open comments and keep the conversation attached to the item
  • Flag, don't duplicate - Flagging a requirement as CP automatically links it into the Client Pending tab, so you do not have to re-type it
  • Watch the summary cards - Overdue and Blocking counts on Client Pending are a quick health check
  • Check the Activity Log for quiet projects - if a project has gone a while without any activity, it will show up as a lower Activity score in the Project Health dialog (click the Project Health stat card at the top of the page to open it)
  • One place for every file - Don't go hunting through tasks and comments for a document โ€” the Files tab already collects everything the project has, including what was attached to Activity Log posts
  • Import in bulk - When a client hands you a long list, download the template, fill it in, and import

๐Ÿ’ก Note: All dialogs can be accessed from the project details page. Use them regularly to keep project information current and track progress effectively.

How It Connects

Set up first

Gets its data from

  • Templates โ€” a project created from a template starts with its tasks, roles and milestones.
  • Project Settings โ€” the client interaction target set there feeds the Project Health score.
  • Discovery โ€” questionnaires sent for this project show up in its Discovery tab.
  • Project Knowledgebase โ€” the project's Knowledgebase tab holds everything agreed with the client.
  • Notes โ€” notes linked to the project show up in its Notes tab.
  • Processes โ€” process runs for the project can be followed in its Processes tab.

Feeds into

  • Timeline โ€” the projectโ€™s task dates are drawn on the cross-project Timeline.
  • Sharing a Project โ€” generate a passcode-protected link so a client can follow the live status without an account.
  • All Tasks โ€” the projectโ€™s tasks also appear in the Tasks page next to your other work.
  • Project Allocation โ€” time tracked on the projectโ€™s tasks is totalled per project.